EVENT
|
TIMELINE
|
Identification of QEP Development Committee Chair and SACS Accreditation Liaison |
August 2005 |
Identification of Institutional Leadership Team |
January 2006 |
Begin process to develop QEP topic |
January 2006 |
Compliance Committees formed |
May 2006 |
Compliance Committees begin work |
September 2006 |
QEP Topic Identified / Begin Researching, Writing, and Supporting QEP |
October 2006 |
* Orientation of Leadership Team |
January 29, 2007 |
Begin Writing Compliance Certification |
September 2007 |
Begin electronic submission development |
October 2007 |
* Visit by SACS Representative, Dr Michael Johnson |
November 20, 2007 |
Compliance Certification Due |
March 17, 2008 |
* Off-site Peer Review Conducted |
May 13-14, 2008 |
Focused Report (Response to Off-Site Preliminary Report) |
Due 6 weeks in advance of onsite visit (Approx. August 25, 2008) |
Quality Enhancement Plan Due |
Due 6 weeks in advance of onsite visit (Approx. August 25, 2008) |
* On-Site Peer Review Conducted |
October 7-9, 2008 |
Response Report Provided (Response to On-Site Committee Report) |
March 2009 |
*Decision by the Commission on Colleges |
June 2009 |
|
|
* SACS COC activities |